PA Energy Projects Approved for Fast-Track Reviews 

PA Energy Projects Approved for Fast-Track Reviews 

Three Pennsylvania energy projects have been selected for PJM’s Expedited Interconnection Track (EIT), a new process designed to help major energy projects quickly connect to the electric grid. The projects include two new battery storage facilities and an expansion of an existing natural gas power plant, expected to add 1.7 gigawatts of generation and storage capacity by mid-2029. The projects will work closely with DEP and DCED regarding expedited state permitting approvals without Governor Shapiro’s GRID proposal. 

The need to bring new energy online has become a major concern in recent years. In its July 2026 capacity auction, PJM fell short of its reliability requirement by more than 6.8 GW, indicating a need for more energy generation and storage to keep up with growing electricity demands. Click here to read the press release and learn more about the EIT-approved projects. 

PA State Association of Township Supervisors

Get In Touch

Mon - Fri, 8:30 am - 4:30 pm

Resources for Township & Municipal Officials

Scroll to Top